UPS Maintenance - DH1-Q2-A

Scheduled Maintenance Report for Namesco Limited

Completed

This maintenance has now been completed successfully with no complications observed.
Posted Nov 21, 2016 - 17:31 GMT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Nov 21, 2016 - 15:30 GMT

Update

As our previous maintenance was completed earlier than expected, we have decided to bring this maintenance forward.

We will start at approximately 15:30.
Posted Nov 21, 2016 - 15:26 GMT

Scheduled

After the power issues on Tuesday, we have thoroughly inspected our systems and identified some parts that need replacing in one of our B side UPS units.
We aim to replace these next Tuesday (22nd November 2016) though we do not have a provisional time for this to be done at this point.

We need to transition from our A feed to our B feed for this portion of the maintenance, and we will be running at reduced resiliency for the duration.

Although we do not anticipate any loss of customer services, please be aware that this maintenance should be considered an "at-risk" period.

We will update this notice when we can give a specific time for the planned maintenance.
Posted Nov 18, 2016 - 15:31 GMT