Datacentre Power Testing
Scheduled Maintenance Report for Namesco Limited
Completed
The scheduled maintenance has been completed.
Posted Jun 18, 2019 - 11:00 BST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jun 18, 2019 - 07:00 BST
Scheduled
During this period we will be performing a load transition onto the generators.

This forms part of our maintenance schedule to ensure that our backup systems will cope with the load.

Power will be transitioned onto the generators for a period of time before being transitioned back to mains again.

All UPS protected equipment should not experience any power loss however this should be considered an at-risk period.