Annual Black Building Test
Scheduled Maintenance Report for Namesco Limited
Completed
All tests have been completed successfully, there will be no further tests and we can now mark this maintenance period as complete.
Posted Oct 28, 2017 - 12:43 BST
Update
The first test has been completed with a transition back onto mains power, we will move onto the second phase of testing shortly.
Posted Oct 28, 2017 - 09:08 BST
Update
Todays tests are under way and we have successfully transitioned to generator power.

We will provide a further update once the test is complete.
Posted Oct 28, 2017 - 09:02 BST
Update
Pre-checks for todays test have been completed and we will start the main test shortly.
Posted Oct 27, 2017 - 12:12 BST
Update
Load has been transferred back to mains power and there will be no further testing done today. Testing will resume tomorrow.
Posted Oct 26, 2017 - 14:23 BST
Update
Load has successfully transitioned to the generators for this portion of the maintenance, we will continue to monitor the situation and update when needed.
Posted Oct 26, 2017 - 12:02 BST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 26, 2017 - 08:00 BST
Scheduled
Starting on the 26th October, we will be performing our annual black building test where we simulate a mains power failure to the building. This maintenance period covers a 3 day window where we will have engineers performing pre-tests, the main generator test itself, and finally post-test checks to ensure that everything worked as expected.

We do not expect any problems or outages, however this period should be considered at-risk as there will be contractors and engineers on-site as well as transitions to and from generator power.
Posted Oct 04, 2017 - 13:59 BST